Logan River Watershed Project awaits funding as federal review continues

 

A proposed $300 million plan to pressurize Logan area irrigation, reduce flood risk and boost river flows is moving through federal review, but no money has been secured to build it. 

The Logan River Watershed Project, which the Natural Resources Conservation Service is reviewing, would put irrigation water in pressurized pipes in Logan, North Logan and Hyde Park, use the existing canals for flood control and add trail connections. Cache Water District is the project’s primary sponsor. 

Nathan Daugs, manager of Cache Water District, said the effort began in 2016, when the Crockett Avenue Irrigation Company, the three cities and the district paid for a feasibility study. The aging Crockett Diversion needed to be rebuilt, so they looked at pressurizing the system at the same time. The project received federal funding in 2021 to begin the environmental review. 

Daugs said the draft environmental impact statement has been submitted for final federal review. He hopes for a record of decision shortly after the first of the year, then the search for funding begins. 

“It’s a big project and it’s not cheap. To do the entire project is just over $300 million,” Daugs said. 

If the federal program were fully funded, he said, it would cover flood control at 100% and irrigation at 75%. Roughly $270 million is needed from the federal government, according to Daugs, and local sponsors would provide about $30 million. 

“We’re not going to get that $300 million in one lump sum,” Daugs said. 

Eric Franson, principal engineer in charge at Franson Civil Engineers, helped lead the engineering team that wrote the environmental impact statement, a document of about 1,500 pages. Franson said the plan changed significantly after public comment. 

“The proposed alternative was modified significantly in response to the public comments that were received,” Franson said. 

The plan would also add 25 cubic feet per second to the Logan River. Daugs said, working with Utah State University and the Logan River Observatory, the team found the added water would keep 13 miles of the river suitable as a cold-water fishery. 

“Where currently, in a year like this, it didn’t meet that for much of the summer,” Daugs said. 

The project would also reuse five of Logan City’s seven sewage lagoons, which are no longer needed after the city’s wastewater plant upgrade. The lagoons would hold just over 2,000 acre-feet of water for late-season irrigation. 

“We saw an opportunity to use some infrastructure that was no longer needed for its original purpose,” Franson said. 

Flood protection is the project’s largest cost, Daugs said. Rebuilding the diversion could remove about 28 nearby homes from a flood zone, and the canals would be enlarged to carry flood water. 

Franson said the diversion must be rebuilt whether or not the larger project moves forward. 

“The Crockett Diversion needs to be replaced whether the overall project happens or not,” Franson said. 

Daugs said the canal companies have applied for a grant for the work. He hopes funding comes next year, with construction probably in 2028 after the irrigation season. 

Pressurizing the system would let outdoor landscaping use untreated secondary water, Daugs said, delaying the need for new culinary water development in the three cities by 40 to 50 years. 

“It’s really a great water security project for the residents of those three cities and the county as a whole,” Daugs said.  

Gordon Coulson, president of Crockett Avenue Irrigation Company, which comprises 10 canal companies, wrote in an email he supports pressurization. 

“I personally fully support the idea of pressurizing the secondary water to be used for outdoor irrigation,” Coulson wrote. “I have seen large benefits to doing this in other parts of the state.” 

Cost to water users remains unsettled. Daugs said shareholders should probably expect higher assessments, though each of the 10 canal companies has a different assessment now, and the project is only at 30% design. 

“It’s not going to be free to the share,” Daugs said. 

Coulson said he is concerned about future costs, but he expects some users to see increases and others to see decreases. 

“Do we expect increases? Yes, for some, however others who use culinary water for outdoor use could see decreases,” Coulson wrote. 

Franson said the intent is to seek enough grants to avoid raising water costs. 

“Our intent would be to find as much grant money as we could so that it didn’t increase their cost of water on the west side, or anywhere for that matter,” Franson said. 

Daugs said construction would take eight to 10 years, with disruptions where large pipes go under roads. 

Franson said his team hopes to stay involved through design and construction if funding is found. 

“In order for the project to be implemented, we have to find some funding,” Franson said. 